Conduct a pre-start toolbox talk with all personnel to review tasks, hazards, and emergency procedures.
Always leave a minimum of one counter-weight block in place (or as directed by the manual) to maintain structural balance before the main jib is removed. Step 4: Jib Removal tower crane dismantling method statement
High-tensile mast bolts must never be forced or cut. Pins must be removed using non-sparking brass drifts. Bolted joints must be loosened systematically following structural loading principles. Conduct a pre-start toolbox talk with all personnel
[Counter-Jib Weights] ➔ [Jib Assembly] ➔ [Counter-Jib] ➔ [Slewing Unit & Cabin] ➔ [Tower Mast Sections] Step 1: Position and Setup the Assist Crane Pins must be removed using non-sparking brass drifts
A Tower Crane Dismantling Method Statement is a critical document that ensures the safe and efficient dismantling of a tower crane. The statement outlines the steps and procedures for dismantling the crane, including pre-dismantling planning, dismantling methods, dismantling procedures, safety procedures, environmental considerations, and quality control measures. By following this method statement, the risk of accidents and incidents can be minimized, and the dismantling process can be completed safely and efficiently.
Position the trolley at the manufacturer’s specified "dismantling radius" to achieve structural equilibrium.